5.8. Measurement (MS)
This performance domain covers the activities and functions associated with assessing project performance and taking appropriate actions to maintain acceptable performance. Measurement in PMBoK 7th edition goes beyond EVM to encompass a broader set of value-focused metrics.
| Knowledge Area (KA) | Core Tier1 | Core Tier2 |
5.8.1 Key Performance Indicators | 1 | 1 |
5.8.2 Dashboards and Information Radiators | 1 | 1 |
5.8.3 Measurement Purpose and Approach | Elective | |
5.8.4 Earned Value and Schedule Performance | Elective | |
5.8.5 Forecasting and Trends | Elective | |
5.8.6 Stakeholder Performance Reporting | Elective | |
5.8.7 Lessons Learned and Knowledge Capture | Elective | |
5.8.1. MS/Key Performance Indicators (Core Tier1: 1 hr, Core Tier2: 1 hr) ↑ Back to top
Defining, selecting, and using key performance indicators (KPIs) to track project health across scope, schedule, cost, quality, and value dimensions.
Topics:
Core
- Selecting KPIs: relevance to project objectives, measurability, and actionability
- Balanced metric sets: leading and lagging indicators, outcome and output metrics
- Setting KPI thresholds and alert levels for triggering corrective action
- Reviewing and adapting the KPI set as the project evolves and stakeholder priorities shift
Learning Outcomes:
Core:
- Define a balanced KPI set for monitoring a project across multiple performance dimensions [Usage]
- Evaluate a given set of KPIs for balance, relevance, and potential for metric dysfunction [Assessment]
- Design a KPI review cycle that keeps performance metrics aligned with evolving project objectives [Assessment]
5.8.2. MS/Dashboards and Information Radiators (Core Tier1: 1 hr, Core Tier2: 1 hr) ↑ Back to top
Using visual management tools to make project performance visible to the team and stakeholders. Covers dashboards, kanban boards, burndown charts, and physical information radiators.
Topics:
Core
- Designing effective project dashboards: key metrics, visual clarity, and stakeholder relevance
- Information radiators: physical and digital tools for continuous team transparency
- Real-time dashboards: automated data feeds and live project status visualization
- Maintaining and evolving dashboards as the project progresses and information needs change
Learning Outcomes:
Core:
- Design a project performance dashboard with relevant KPIs for team and stakeholder use [Usage]
- Implement information radiators that provide real-time project transparency to the team [Assessment]
- Evaluate the effectiveness of a dashboard in communicating project health and recommend improvements [Assessment]
5.8.3. MS/Measurement Purpose and Approach ↑ Back to top
Understanding why and how to measure project performance. Covers the purpose of measurement, the risk of metric dysfunction, and principles for selecting meaningful measures.
Topics:
Core
- Purpose of measurement: informing decisions, detecting issues, and demonstrating value
- Principles of effective measurement: meaningful, actionable, and timely metrics
- Metric dysfunction: gaming, Goodhart's Law, and the dangers of measuring the wrong things
- Selecting measurement approach based on project type, development approach, and stakeholder needs
Learning Outcomes:
Core:
- Describe the purpose and principles of effective project performance measurement [Familiarity]
- Identify the risk of metric dysfunction and select measures that drive the right behaviors [Usage]
- Design a measurement approach appropriate to the project type and stakeholder needs [Assessment]
5.8.4. MS/Earned Value and Schedule Performance ↑ Back to top
Using Earned Value Management (EVM) and schedule performance indicators to measure project cost and schedule health. Covers EVM metrics, SPI, CPI, and forecasting.
Topics:
Core
- EVM metrics: PV, EV, AC, CV, SV, CPI, SPI
- EVM forecasting: EAC, ETC, VAC, and TCPI
- Applying earned value concepts in adaptive environments: velocity, burndown, and throughput
- Interpreting EVM trends over time to forecast project completion and identify systemic issues
Learning Outcomes:
Core:
- Calculate and interpret EVM metrics to assess project cost and schedule performance [Usage]
- Adapt EVM concepts for use in adaptive project environments [Assessment]
- Use EVM data to forecast project completion cost and schedule and evaluate the accuracy of those forecasts [Assessment]
5.8.5. MS/Forecasting and Trends ↑ Back to top
Using current performance data to forecast future project outcomes. Covers trend analysis, forecasting techniques, and the use of forecasts for proactive management.
Topics:
Core
- Trend analysis: identifying performance patterns to predict future outcomes
- Forecasting techniques: EAC formulas, regression analysis, and expert judgment
- Using forecasts proactively to prevent problems rather than react to them
- Communicating forecast uncertainty: confidence intervals, scenario ranges, and assumptions
Learning Outcomes:
Core:
- Apply trend analysis and forecasting techniques to predict project completion outcomes [Usage]
- Use forecasting data to make proactive project management decisions [Assessment]
- Evaluate the reliability of project forecasts by examining underlying assumptions and comparing against actual results [Assessment]
5.8.6. MS/Stakeholder Performance Reporting ↑ Back to top
Communicating project performance to stakeholders in a format and frequency appropriate to their needs. Covers report design, tailoring, and information transparency.
Topics:
Core
- Designing performance reports: content, format, and frequency tailored to stakeholder needs
- Transparent reporting: honest and complete performance communication including bad news
- Executive-level reporting: summarizing project health for senior stakeholders
- Exception reporting: focusing reporting effort on deviations, risks, and decisions rather than routine status
Learning Outcomes:
Core:
- Prepare a project performance report tailored to a specific stakeholder audience [Usage]
- Design an executive reporting structure that provides meaningful project health information [Assessment]
- Evaluate a project reporting system for transparency, accuracy, and stakeholder relevance [Assessment]
5.8.7. MS/Lessons Learned and Knowledge Capture ↑ Back to top
Systematically capturing, documenting, and disseminating lessons learned throughout and after the project. Covers retrospectives, after-action reviews, and organizational knowledge assets.
Topics:
Core
- Lessons learned process: capture, analysis, documentation, and dissemination
- Retrospectives and after-action reviews: structured team reflection for continuous improvement
- Contributing lessons learned to organizational knowledge repositories and process assets
- Timing and frequency of lessons learned: ongoing capture vs. phase-end reviews vs. project closure
Learning Outcomes:
Core:
- Conduct a lessons learned session and document findings for team and organizational use [Usage]
- Integrate lessons learned into organizational knowledge assets to support future projects [Assessment]
- Design a lessons learned program that captures insights continuously rather than only at project closure [Assessment]